Section 74:12:02:14 - Blowout prevention equipment required

In all drilling operations, precautions must be taken for keeping the well under control, including the use of blowout preventers and high pressure fittings attached to a cemented casing string. If the drilling operation is in an area where a blowout preventer may not be needed, an exception to the blowout preventer requirement may be granted by the secretary.

S.D. Admin. R. 74:12:02:14

38 SDR 117, effective 1/12/2012.

General Authority: SDCL 45-9-11, 45-9-13.