S.D. Admin. R. 74:02:01:33

Current through Register Vol. 51, page 67, December 16, 2024
Section 74:02:01:33 - Information required for temporary permits

A temporary permit must contain the following information:

(1) Name and address of the water user;
(2) Project or projects on which water will be used;
(3) Source of water;
(4) Location of the water diversion points;
(5) Maximum total amount of water to be used (in gallons);
(6) Maximum daily withdrawal rate (in gallons);
(7) Date after which water use can begin;
(8) Date when water use will cease;
(9) Date of issuance of the permit; and
(10) Any qualifications thought necessary by the chief engineer.

S.D. Admin. R. 74:02:01:33

SL 1975, ch 16, § 1; transferred from § 52:01:01:31, effective 7/1/1979; 10 SDR 27, effective 9/26/1983; repealed, 13 SDR 49, effective 10/27/1986; readopted, 13 SDR 186, effective 6/18/1987.

General Authority: SDCL 46-2-5, 46-5-40.1.

Law Implemented: SDCL 46-1-2, 46-2-3.1, 46-2-9, 46-2-11, 46-2-17, 46-5-40.1.