N.D. Cent. Code § 49-09.1-04

Current through 2024 Legislative Session
Section 49-09.1-04 - Commencement of construction across railroad right of way

Thirty-five days after the receipt by the railroad of the completed crossing application, crossing fee, and certificate of insurance, the utility may commence the construction of the crossing, unless the railroad notifies the utility in writing that the proposed crossing is a serious threat to the safe operations of the railroad or to the current use of the railroad right of way. In all other instances, the utility is deemed to have authorization to commence construction of the facility.

N.D.C.C. § 49-09.1-04

Added by S.L. 2019, ch. 387 (HB 1362),§ 1, eff. 8/1/2019.
See S.L. 2019, ch. 387 (HB 1362), § 2.