Current through the 2023 Legislative Sessions
Section 49-09.1-03 - Notice and application for placement1. A utility that intends to place a facility across a railroad right of way shall provide notice of the placement to the railroad at least thirty days before the placement.2. The notice must include a completed crossing application, including a drawing showing the location of the proposed crossing and the railroad's property, tracks, and wires the utility will cross.3. The utility shall submit the crossing application on a form provided or approved by the railroad, if available.4. The crossing application must be sent to the railroad by registered mail.5. The application must be accompanied by the crossing fee in section 49-09.1-05, and a certificate of insurance as required in section 49-09.1-06.Added by S.L. 2019, ch. 387 (HB 1362),§ 1, eff. 8/1/2019. See S.L. 2019, ch. 387 (HB 1362), § 2.