Each utility issued a certificate of public convenience and necessity for a specific project or extension shall:
(a) Report the date construction will commence as soon as it is known, but no later than five business days prior to commencement;
(b) Submit monthly construction progress reports;
(c) Report the date construction was completed within 20 business days of completion; and
(d) Submit a report no later than 180 days following completion of construction that includes: - (iv) Material costs by general category;
- (v) Administrative and general expenses;
- (vii) Right-of-way costs;
- (viii) Costs and rates used to calculate Allowance for Funds Used During Construction;
- (ix) Other costs for which the utility will seek recovery for in rates and how items (iii) through (vii) were accounted for in its books and records;
- (x) Proposed depreciation rates;
- (xi) Journal entries transferring the completed project from Construction Work in Progress to Utility Plant in Service by account number;
- (xii) For facility modifications, journal entries recording any plant retired and appropriate account numbers for utility plant and reserve for depreciation;
- (xiii) For facility modifications, journal entries recording any plant salvage values and decommissioning costs or sale of any plant retired;
- (xiv) Contact information for contractors that performed work;
- (xv) Conditions (terrain, location, weather, etc.) under which construction was performed;
- (xvi) Any non-standard facility feature; and
- (xvii) Completed project maps and engineering drawings, if changed from those previously submitted.
023-3 Wyo. Code R. § 3-22