(a) At the jurisdictional meeting the Administrator shall specify the study area for the project application. The study area provides the boundaries for studies of counties and municipalities.
(b) The applicant shall notify and describe the project to local governments in the study area. The notice and description shall be sent by certified mail, return receipt, and shall include a description of the project, its location, the expected construction period, the number of construction workers, transportation routes for construction materials, the anticipated economic benefits of the project, the anticipated impacts from the project and offer methods to comment to the applicant and attend scheduled informational meetings. The notice and description will be mailed no later than 10 business days prior to the first informational meeting.
(c) The date of filing of an application is that date when all of the following have been received by the Division:
(d) When the application is filed, the Division shall provide the applicant with a written receipt for the application which shall stipulate the application has been filed on that date.
(e) After receipt and examination of the application the Administrator shall determine the area primarily affected.
(f) Counties who wish to make a referral according to W.S. 18-5-509 shall provide the following:
020-1 Wyo. Code R. § 1-5
Amended, Eff. 4/4/2017.
Amended, Eff. 8/9/2018.