GENERAL INFORMATION | ||
Manufacture: | Manufacturer # | |
1. Building use: | 2. Building occupancy: | |
3. Type of construction: | 4. Square footage of building: | |
5. Valuation of the building shall be based on the following: | ||
* Square footage of the building multiplied by the amount in the BVD valuation table ................................................... | $ ..... | |
6. Total valuation: ......................................................... | $ ..... | |
PERMIT FEE | ||
7. Calculate from building permit fee table using the total valuation .................. | $ ..... | |
STRUCTURAL PLAN REVIEW FEE* | ||
8. One year design review: (Valid for one year) multiply the total on line 7 by 0.483 .......................................... | $ ..... | |
9. Master plan review: (Valid for the code cycle) multiply the total on line 7 by 0.690 ................................... | $ ..... | |
* Minimum plan review fee is 2 1/2 hours x $118.20 per hour | ||
FIRE AND LIFE-SAFETY PLAN REVIEW FEE (if required) | ||
10. Fire and life-safety plan review: | ||
a. One year design-Multiply the total on line 7 by 0.206 ................... | $ ..... | |
b. Master plan design-Multiply the total on line 7 by 0.343 ................ | $ ..... | |
* Required for all structures that are more than 4,000 square feet and for all A, I, and H occupancy | ||
PLUMBING PLAN-REVIEW FEE | ||
11. Plumbing $24.60 + $7.90 per fixture .......................... | $ ..... | |
12. Medical gas $24.60 + $7.90 per gas outlet ..................... | $ ..... | |
DESIGN RENEWAL OR ADDENDUM | ||
13. 13.82% of building permit + $118.20 ...................... | ||
RESUBMITTAL | ||
14. 13.82% of building permit + $118.20 ...................... | ||
ELECTRICAL PLAN-REVIEW FEE | ||
15. See WAC 296-46B-906(9) for electrical review fees | ||
NOTIFICATION TO LOCAL ENFORCEMENT AGENCY (NLEA) | ||
16. Notification to local enforcement agency fee: | $ 50.70 | |
INSIGNIA FEES | ||
17. FIRST SECTION | $ 378.30 | |
18. EACH ADDITIONAL SECTION | $ 33.60 | |
TOTAL FEES | ||
19. Total plan review fees: Add lines 8 or 9 and 10 through 15 ................... | $ ..... | |
20. Total fees due: Includes plan fees, insignia fees, and NLEA fees ........ | $ ..... | |
21. Total amount paid ...................................................... | $ ..... |
Square Foot Construction Costs (BVD Table)a, b, c, and d
Group (2009 International Building Code) | IA | IB | IIA | IIB | IIIA | IIIB | IV | VA | VB |
A-1 Assembly, theaters, with stage | 211.15 | 203.98 | 198.73 | 190.05 | 178.25 | 173.30 | 183.31 | 162.97 | 156.05 |
A-1 Assembly, theaters, without stage | 193.16 | 185.99 | 180.74 | 172.06 | 160.31 | 155.36 | 165.32 | 145.04 | 138.12 |
A-2 Assembly, nightclubs | 163.22 | 158.56 | 154.17 | 148.00 | 138.96 | 135.24 | 142.52 | 126.06 | 121.36 |
A-2 Assembly, restaurants, bars, banquet halls | 162.22 | 157.56 | 152.17 | 147.00 | 136.96 | 134.24 | 141.52 | 124.06 | 120.36 |
A-3 Assembly, churches | 195.10 | 187.93 | 182.68 | 174.00 | 162.21 | 157.26 | 167.26 | 146.94 | 140.02 |
A-3 Assembly, general, community halls, libraries, museums | 163.81 | 156.64 | 150.39 | 142.71 | 129.91 | 125.96 | 135.97 | 114.63 | 108.71 |
A-4 Assembly, arenas | 192.16 | 184.99 | 178.74 | 171.06 | 158.31 | 154.36 | 164.32 | 143.04 | 137.12 |
B Business | 164.76 | 158.78 | 153.49 | 145.97 | 132.45 | 127.63 | 139.92 | 116.43 | 110.93 |
E Educational | 176.97 | 170.85 | 165.64 | 158.05 | 146.37 | 138.98 | 152.61 | 127.91 | 123.09 |
F-1 Factory and industrial, moderate hazard | 97.87 | 93.28 | 87.66 | 84.46 | 75.44 | 72.26 | 80.79 | 62.17 | 58.48 |
F-2 Factory and industrial, low hazard | 96.87 | 92.28 | 87.66 | 83.46 | 75.44 | 71.26 | 79.79 | 62.17 | 57.48 |
H-1 High hazard, explosives | 91.74 | 87.15 | 82.53 | 78.33 | 70.49 | 66.31 | 74.66 | 57.22 | N.P. |
H-2, 3, 4 High hazard | 91.74 | 87.15 | 82.53 | 78.33 | 70.49 | 66.31 | 74.66 | 57.22 | 52.53 |
H-5 HPM | 164.76 | 158.78 | 153.49 | 145.97 | 132.45 | 127.63 | 139.92 | 116.43 | 110.93 |
I-1 Institutional, supervised environment | 164.82 | 159.04 | 154.60 | 147.90 | 135.84 | 132.25 | 144.15 | 121.88 | 117.55 |
I-2 Institutional, hospitals | 277.07 | 271.09 | 265.80 | 258.28 | 243.90 | N.P. | 252.23 | 227.88 | N.P. |
I-2 Institutional, nursing homes | 193.00 | 187.02 | 181.74 | 174.22 | 160.98 | N.P. | 168.16 | 144.96 | N.P. |
I-3 Institutional, restrained | 187.72 | 181.73 | 176.45 | 168.93 | 156.64 | 150.82 | 162.87 | 140.63 | 133.13 |
I-4 Institutional, day care facilities | 164.82 | 159.04 | 154.60 | 147.90 | 135.84 | 132.25 | 144.15 | 121.88 | 117.55 |
M Mercantile | 121.57 | 116.92 | 111.53 | 106.36 | 96.96 | 94.25 | 100.88 | 84.07 | 80.36 |
R-1 Residential, hotels | 166.21 | 160.43 | 155.99 | 149.29 | 137.39 | 133.80 | 145.70 | 123.43 | 119.10 |
R-2 Residential, multiple family | 139.39 | 133.61 | 129.17 | 122.47 | 111.23 | 107.64 | 119.54 | 97.27 | 92.94 |
R-3 Residential, one and two family | 131.18 | 127.60 | 124.36 | 121.27 | 116.43 | 113.53 | 117.42 | 108.79 | 101.90 |
R-4 Residential, care/ assisted living facilities | 164.82 | 159.04 | 154.60 | 147.90 | 135.84 | 132.25 | 144.15 | 121.88 | 117.55 |
S-1 Storage, moderate hazard | 90.74 | 86.15 | 80.53 | 77.33 | 68.49 | 65.31 | 73.66 | 55.22 | 51.53 |
S-2 Storage, low hazard | 89.74 | 85.15 | 80.53 | 76.33 | 68.49 | 64.31 | 72.66 | 55.22 | 50.53 |
U Utility, miscellaneous | 71.03 | 67.02 | 62.71 | 59.30 | 52.86 | 49.43 | 56.33 | 41.00 | 39.06 |
a Private garages use utility, miscellaneous
b Unfinished basements (all use group) = $15.00 per sq. ft.
c For shell only buildings deduct 20 percent
d N.P. = not permitted
Table 1-A - Building Permit Fees
Total Valuation | Fee |
$1.00 to $500.00 | $23.50 |
$501.00 to $2,000.00 | $23.50 for the first $500.00 plus $3.05 for each additional $100.00, or fraction thereof, to and including $2,000.00 |
$2,001.00 to $25,000.00 | $69.25 for the first $2,000.00 plus $14.00 for each additional $1,000.00, or fraction thereof, to and including $25,000.00 |
$25,001.00 to $50,000.00 | $391.25 for the first $25,000.00 plus $10.10 for each additional $1,000.00, or fraction thereof, to and including $50,000.00 |
$50,001.00 to $100,000.00 | $643.75 for the first $50,000.00 plus $7.00 for each additional $1,000.00, or fraction thereof, to and including $100,000.00 |
$100,001.00 to $500,000.00 | $993.75 for the first $100,000.00 plus $5.60 for each additional $1,000.00, or fraction thereof, to and including $500,000.00 |
$500,001.00 to $1,000,000.00 | $3,233.75 for the first $500,000.00 plus $4.75 for each additional $1,000.00, or fraction thereof, to and including $1,000,000.00 |
$1,000,001.00 and up | $5,608.75 for the first $1,000,000.00 plus $3.65 for each additional $1,000.00, or fraction thereof |
INITIAL FILING FEE (first time applicants) | $92.20 |
DESIGN PLAN FEES: | |
INITIAL FEE - MASTER DESIGN (code cycle), 50% of permit fee × 1.382* | |
INITIAL FEE - ONE YEAR DESIGN, 35% of permit fee × 1.382* | |
RENEWAL FEE - 10% of permit fee × 1.382 + | $118.20 |
RESUBMIT FEE - 10% of permit fee × 1.382 + | $118.20 |
ADDENDUM (approval expires on same date as original plan) - 10% of permit fee × 1.382 + | $118.20 |
PLUMBING PLAN FEE, $24.60 + PER FIXTURE FEE of | $7.90 |
MEDICAL GAS PLAN FEE, $24.60 + PER OUTLET FEE of | $7.90 |
Note: Mechanical systems are included in the primary plan fee | |
FIRE SAFETY PLAN REVIEW AS REQUIRED (Required for all structures that are more than 4,000 square feet and for all A, I, and H occupancy) | |
MASTER DESIGN - 25% of permit fee × 1.382 | |
One year design - 15% of the permit fee × 1.382 | |
ELECTRICAL PLAN REVIEW - Find fees @ http://apps.leg.wa.gov/wac/default.aspx?cite=296-46B-906 | |
RECIPROCAL PLAN REVIEW: | |
INITIAL FEE-MASTER DESIGN (minimum 3 hours) | $118.20 per hour |
INITIAL FEE-ONE YEAR DESIGN (minimum 2 hours) | $118.20 per hour |
RENEWAL FEE (minimum 1 hour) | $118.20 |
ADDENDUM (minimum 1 hour) | $118.20 per hour |
PLANS APPROVED BY LICENSED PROFESSIONALS - 10% of permit fee × 1.382 + | $118.20 |
FEES FOR RESUBMITTAL OF DESIGN PLANS APPROVED BY A PROFESSIONAL OR FIRM | $118.20 per hour |
APPROVAL OF EACH SET OF DESIGN PLANS BEYOND FIRST THREE SETS - 5% of permit fee × 1.382 + | $118.20 |
DEPARTMENT INSPECTION FEES | |
INSPECTION/REINSPECTION (Per hour** plus travel time** and mileage***) | $118.20 |
TRAVEL (Per hour**) | $118.20 |
PER DIEM*** | |
HOTEL**** | |
MILEAGE*** | |
RENTAL CAR**** | |
PARKING**** | |
AIRFARE**** | |
DEPARTMENT AUDIT FEES: | |
AUDIT (Per hour**) | $118.20 |
TRAVEL (Per hour**) | $118.20 |
PER DIEM*** | |
HOTEL**** | |
MILEAGE*** | |
RENTAL CAR**** | |
PARKING**** | |
AIRFARE**** | |
INSIGNIA FEES: | |
FIRST SECTION | $378.30 |
EACH ADDITIONAL SECTION | $33.60 |
REISSUED-LOST/DAMAGED | $92.20 |
OTHER FEES: | |
FIELD TECHNICAL SERVICE (Per hour** plus travel time** and mileage***) | $118.20 |
NOTIFICATION TO LOCAL ENFORCEMENT AGENCY (NLEA) | $50.70 |
PUBLICATION PRINTING AND DISTRIBUTION OF RCWs AND WACs (One free copy per year upon request) | $18.70 |
REFUND FEE | $34.30 |
*Minimum plan review fee is 2 1/2 hours at the field technical service rate.
**Minimum charge of 1 hour; time spent greater than 1 hour is charged in 1/2 hour increments.
***Per state guidelines.
****Actual charges incurred.
Wash. Admin. Code § 296-150F-3000
Statutory Authority: Chapter 43.22 RCW and 2011 1st sp.s. c 50. 12-06-069, § 296-150F-3000, filed 3/6/12, effective 4/30/12. Statutory Authority: Chapters 18.106, 43.22 RCW, 2008 c 285 and c 329. 08-12-042, § 296-150F-3000, filed 5/30/08, effective 6/30/08. Statutory Authority: Chapters 18.27, 18.106, 43.22, and 70.87 RCW. 07-11-128, § 296-150F-3000, filed 5/22/07, effective 6/30/07. Statutory Authority: Chapter 43.22 RCW. 07-05-063, § 296-150F-3000, filed 2/20/07, effective 4/1/07. Statutory Authority: Chapters 18.106, 43.22, and 70.87 RCW. 06-10-066, § 296-150F-3000, filed 5/2/06, effective 6/30/06. Statutory Authority: Chapter 43.22 RCW. 05-23-002, § 296-150F-3000, filed 11/3/05, effective 12/4/05. Statutory Authority: Chapters 18.27, 43.22, and 70.87 RCW. 05-12-032, § 296-150F-3000, filed 5/24/05, effective 6/30/05. Statutory Authority: Chapter 43.22 RCW and 2003 c 291. 05-01-102, § 296-150F-3000, filed 12/14/04, effective 2/1/05. Statutory Authority: Chapters 18.27 and 43.22 RCW. 04-12-048, § 296-150F-3000, filed 5/28/04, effective 6/30/04. Statutory Authority: RCW 43.22.340, 43.22.400, 43.22.432, 43.22.433, 43.22.434, 43.22.480, and 43.22.485, 2002 c 268, and chapter 43.22 RCW. 03-12-044, § 296-150F-3000, filed 5/30/03, effective 5/30/03. Statutory Authority: RCW 43.22.350, 43.22.434, 43.22.480, 43.22.500, 18.27.070, 18.27.075, 70.87.030, 19.28.041, 19.28.051, 19.28.101, 19.28.121, 19.28.161, 19.28.201, 19.28.211, 19.28.341, 2001 c 159, and chapters 43.22, 19.28, 18.27, and 70.87 RCW. 01-12-035, § 296-150F-3000, filed 5/29/01, effective 6/29/01. Statutory Authority: Chapters 43.22, 18.27, 70.87 and 19.28 RCW. 99-12-080, § 296-150F-3000, filed 5/28/99, effective 6/28/99. Statutory Authority: Chapters 18.106, 18.27 and 43.22 RCW. 98-12-041, § 296-150F-3000, filed 5/29/98, effective 6/30/98. Statutory Authority: RCW 70.87.030, 18.27.070, [18.27.]075,43.22.350 , [43.22.]355, [43.22.]434 and [43.22.]480(2). 97-11-053, § 296-150F-3000, filed 5/20/97, effective 6/30/97. Statutory Authority: RCW 43.22.340, [43.22.]355, [43.22.]360,[43.22.]432 , [43.22.]440 and [43.22.]480. 96-21-146, § 296-150F-3000, filed 10/23/96, effective 11/25/96.