Current through Bulletin 2024-23, December 1, 2024
Section R746-312-11 - Interconnection Metering(1) Metering: For generating facilities not subject to Title 54, Chapter 15, Net Metering of Electricity, the interconnection customer shall be responsible for the buying and installation of any special metering and data acquisition equipment considered necessary under the terms of the interconnection agreement unless the public utility determines otherwise. The public utility must install, maintain, and operate the metering equipment. The parties must mutually grant unrestricted access to this equipment as may be necessary to conduct routine business.(2) For generating facilities subject to Title 54, Chapter 15, Net Metering of Electricity, metering equipment and costs for this metering equipment shall be determined as specified in Section 54-15-103. The public utility must install, maintain, and operate the metering equipment. The parties must mutually grant unrestricted access to this equipment as may be necessary to conduct routine business.Utah Admin. Code R746-312-11
Amended by Utah State Bulletin Number 2017-2, effective 12/22/2016Amended by Utah State Bulletin Number 2024-08, effective 4/9/2024