Phase 1: Foundation materials for footing, stem wall, piers, rebar, anchor bolts, and redwood or treated lumber
Phase 2: House Shell materials for framing, trusses, OSB plywood, siding, roofing, vents
Phase 3: Exterior Doors and Windows
Phase 4: Rough-in House wiring and Plumbing
Phase 5: Insulation and Drywall
Phase 6: Flooring
Phase 7: Finish Carpentry: Cabinets, Casing and Baseboard, Exterior trim, Soffit, Interior and Exterior Painting
Phase 8: Finish House wiring and Plumbing
Utah Admin. Code R661-7-601