Utah Admin. Code 131-4-820

Current through Bulletin 2024-23, December 1, 2024
Section R131-4-820 - Interest Rate

The board recognizes Section 63G-6-820 as being applicable and therefore:

(1) Except as provided in (2) below, in controversies between the board, including the executive director, and contractors under R131-4-801 through R131-4-820, interest on amounts ultimately determined to be due to a contractor or to the board and the state are payable at the rate applicable to judgments from the date the claim arose through the date of decision or judgment, whichever is later.
(2) This rule does not apply to public assistance benefits programs.

Utah Admin. Code R131-4-820