Operators of a new injection well shall submit a complete application at least 270 days before the date construction is expected to begin unless the new well is covered by an area permit.
S.D. Admin. R. 74:55:01:04
General Authority: SDCL 34A-2-93(15).
Law Implemented: SDCL 34A-2-28.