Section 74:36:20:19 - Procedures to reopen construction permit

The department shall notify the source at least 30 days before reopening a construction permit. The department may reopen a permit in a shorter time in an emergency. The procedures to reopen a construction permit shall follow the procedural requirements to issue a construction permit and shall affect only those parts of the permit for which cause to reopen exists.

S.D. Admin. R. 74:36:20:19

36 SDR 207, effective 6/28/2010.

General Authority: SDCL 34A-1-6, 34A-1-21.