The department may reopen a construction permit for further review if the department determines that the permit contains a material mistake in establishing the emissions standards or limits or other requirements of the construction permit or the department determines that the construction permit must be revised to ensure compliance with the applicable requirements of this article and the Clean Air Act.
S.D. Admin. R. 74:36:20:18
General Authority: SDCL 34A-1-6, 34A-1-21.
Law Implemented: SDCL 34A-1-21.