Current through Register Vol. 51, page 67, December 16, 2024
Section 74:36:20:07 - Required contents of complete application for a construction permitAn application for a construction permit for a new source or modification must include the following information to be considered a complete application:
(1) The following general company information:(a) The company name and address or the plant name and address if different from the company name;(b) The owner's name and agent; and(c) The plant site manager or contact;(2) A description of the plant and its processes and products;(3) The following information on emissions: (a) Identification and description of all emission units;(b) Fuels, fuel use, raw materials, and production rates;(c) Identification and description of air pollution control equipment;(d) Limitations on source operation affecting emissions or any work practice standards, if applicable, for all regulated air pollutants;(e) Other information required by any applicable requirements, including information related to stack height limits, such as the location of emission units, flow rates, building dimensions, and stack parameters, including height, diameter, and plume temperature, for all pollutants regulated at the source;(4) If available, a copy of any prepared plans and the specifications of any equipment or other facilities that may affect the source, including pollution control devices;(5) A signed and notarized certification of applicant form;(6) The results of any air dispersion modeling required by the department;(7) The results of any stack performance testing required by the department; and(8) Any other information requested by the department that is relevant to determining compliance with the act or the Clean Air Act. The application must be signed by the responsible official or designated representative.
S.D. Admin. R. 74:36:20:07
36 SDR 207, effective 6/28/2010.General Authority: SDCL 34A-1-6, 34A-1-21.
Law Implemented: SDCL 34A-1-12, 34A-1-21.