A person who constructs a new source or modification to an existing source required to have a construction permit shall submit a complete application to the department at least 180 days before the estimated date of commencing construction of the new source or modification to an existing source. An application is complete if it meets the requirements in § 74:36:20:07.
S.D. Admin. R. 74:36:20:06
General Authority: SDCL 34A-1-6, 34A-1-21.