Treatment of the tailings shall continue until the effluent or pore water from the tailings impoundment meets the following criteria as determined by using a statistical method agreed upon by the department and the operator:
If the criteria in this section prove to be inappropriate, alternate site-specific criteria based on a pathway and fate analysis may be developed by the department; and the board of water management may require that a state surface water or groundwater discharge permit be obtained in accordance with chapter 74:52:01 or 74:54:02, as applicable.
If future sampling according to the standards in this section proves treatment to be inadequate, other criteria may be specified by the department on a site-specific basis.
S.D. Admin. R. 74:29:05:08
General Authority: SDCL 45-6B-81.
Law Implemented: SDCL 45-6B-44, 45-6B-45.