Section 74:12:05:02 - Method for making pressure tests - Special orders - Filing

Each operator shall measure the shut-in pressure on all wells with a calibrated gauge annually. Shut-in pressure tests shall be performed after the well has been shut-in for at least 24 hours. Results of the tests shall be filed with the secretary.

S.D. Admin. R. 74:12:05:02

38 SDR 117, effective 1/12/2012.

General Authority: SDCL 45-9-13.

Law Implemented: SDCL 45-9-6.