Section 74:02:04:21 - Permits required before construction of certain wells

Before drilling a well for which a water permit is required, the well owner shall obtain a permit pursuant to SDCL 46-1-15, 46-2A-9, and 46-5-10. Following a request, the chief engineer may authorize construction of a test well prior to approval of a permit. The construction and testing does not constitute construction of works for appropriation of water pursuant to SDCL 46-5-9.

S.D. Admin. R. 74:02:04:21

12 SDR 50, effective 9/29/1985; 13 SDR 129, 13 SDR 141, effective 7/1/1987; 18 SDR 224, effective 7/16/1992.

General Authority: SDCL 46-2-5.

Law Implemented: SDCL 46-1-15, 46-2A-9, 46-5-10.