S.D. Admin. R. 74:02:01:48

Current through Register Vol. 51, page 67, December 16, 2024
Section 74:02:01:48 - Petitioner to notify all affected persons

The petitioner shall serve a copy of the petition upon all known persons whose pecuniary interests would be directly and immediately affected by a declaratory ruling on the petition. Proof of such service shall be filed with the board with the petition. All such parties shall be notified by the chief engineer at least 15 days before the petition is scheduled to be heard. In addition, the petitioner shall publish a notice of hearing describing the contents of the petition pursuant to SDCL 46-2A-4(1) to 46-2A-4(10), as applicable, and SDCL 1-26-17.

S.D. Admin. R. 74:02:01:48

9 SDR 96, effective 1/30/1983; 13 SDR 129, 13 SDR 141, effective 7/1/1987; 17 SDR 40, effective 9/19/1990.

General Authority: SDCL 46-2-5.

Law Implemented: SDCL 1-26-15, 1-26-17.1, 46-2-5.