Section 61:08:09:37 - External inspection - Blowoff piping requirements

The blowdown of the boiler must be demonstrated to the inspector in a sufficient amount to ensure that the valve is functioning properly. The valve must be attached as described in § 61:08:09:20 or the boiler must be equipped as original.

S.D. Admin. R. 61:08:09:37

23 SDR 139, effective 3/5/1997.

General Authority: SDCL 34-29A-14.1.