S.D. Admin. R. 61:08:09:28

Current through Register Vol. 51, page 67, December 16, 2024
Section 61:08:09:28 - Duration of hydrostatic test

The hydrostatic test pressure must be held long enough for the inspector to thoroughly examine the boiler for leaks and any evidence of failure. All sheets, plates, and seams must be examined for leaks and bulging and all piping and accessories must be examined for leaks and evidence of failures.

S.D. Admin. R. 61:08:09:28

23 SDR 139, effective 3/5/1997.

General Authority: SDCL 34-29A-14.1.

Law Implemented: SDCL 34-29A-14.1.