Prior to use, all equipment must be approved for supplemental power generation pursuant to § 20:44:22:03 and National Electrical Code, Section 110-3. If equipment is not listed by a qualified electrical laboratory, it must be approved or disapproved by the commission or its designee according to the National Electrical Code, Article 90-4, before installation. Any costs incurred in this procedure are the responsibility of the owner of the cogeneration facility.
S.D. Admin. R. 20:44:25:04
General Authority: SDCL 36-16-12.
Law Implemented: SDCL 36-16-27.