Prior to the legal excavation start date and time, the operator shall communicate with the excavator if, based on information in the ticket, the operator believes a high profile underground facility is in close proximity to the excavation site. If it is determined by the operator that no high profile underground facility is at risk, the operator may allow the excavator to commence excavation without a site meeting. The excavator may proceed and excavate according to all other rules and statutes.
If the operator is either unable to clearly identify the specific excavation site or determines that the excavation site may be in close proximity to the high profile underground facility, the following steps shall be taken prior to the legal excavation start date and time:
S.D. Admin. R. 20:25:03:10.02
General Authority: SDCL 49-7A-4.
Law Implemented: SDCL 49-7A-2, 49-7A-5, 49-7A-8.