Current through Register Vol. 51, page 67, December 16, 2024
Section 20:10:36:44 - Tier 3 interconnection alternate evaluation and screening criteriaFor a small generator facility to interconnect to a distribution circuit that is not networked, the following criteria shall be met for a tier 3 interconnection:
(1) The small generator facility has an electric nameplate capacity of 10 megawatts or less;(2) The aggregated total of the electric nameplate capacity of all of the generators on the circuit, including existing FERC wholesale generators, FERC wholesale generators with a higher queue position, and the proposed small generator facility, is 10 megawatts or less;(3) The small generator facility does not export power beyond the point of interconnection and employs reverse power relays or other protection functions that prevent power flow onto the EDS;(4) The small generator facility's proposed interconnection is to a radial distribution circuit;(5) The small generator facility is not served by a shared transformer;(6) The interconnection will use only existing public utility facilities and the applicant's proposed facilities; and(7) If the public utility's distribution circuit utilizes high speed reclosing with less than 2 seconds of interruption, the proposed generator may not be a synchronous machine.S.D. Admin. R. 20:10:36:44
35 SDR 305, effective 7/1/2009.General Authority: SDCL 49-34A-27, 49-34A-93.
Law Implemented: SDCL 49-34A-27, 49-34A-93.