A tier 3 small generator facility meeting all tier 3 evaluation and screening criteria shall be further evaluated using tier 2 evaluation and screening criteria, except that the 15 percent tier 2 screen does not apply to tier 3 small generator facilities.
Tier 3 interconnections do not require an interconnection feasibility study. However, the public utility may choose to conduct such a study at its own expense, and it must complete the interconnection feasibility study within 25 calendar days.
For a small generator facility to interconnect to the load side of an area network distribution circuit, the following criteria must be met:
S.D. Admin. R. 20:10:36:43
General Authority: SDCL 49-34A-27, 49-34A-93.
Law Implemented: SDCL 49-34A-27, 49-34A-93.