A public utility shall require the applicant to provide commissioning notice or notice of intent to begin operations of a small generation facility to the public utility. A tier 1 application shall provide 10 business days notice. A tier 2, tier 3, or tier 4 application shall provide 20 business days notice.
S.D. Admin. R. 20:10:36:05
General Authority: SDCL 49-34A-27, 49-34A-93.
Law Implemented: SDCL 49-34A-27, 49-34A-93.