S.D. Admin. R. 20:10:36:04

Current through Register Vol. 51, page 67, December 16, 2024
Section 20:10:36:04 - Application for interconnection

A public utility shall require an applicant who wants to interconnect, make a capacity change, or change the status of a proposed or operating facility to submit an application to the public utility that owns and operates the EDS to which interconnection is sought. Each public utility shall review all interconnection requests submitted to the public utility at its authorized mailing address.

S.D. Admin. R. 20:10:36:04

35 SDR 305, effective 7/1/2009.

General Authority: SDCL 49-34A-27, 49-34A-93.

Law Implemented: SDCL 49-34A-27, 49-34A-93.