Current through Register Vol. 51, page 67, December 16, 2024
Section 20:10:21:05 - Proposed energy conversion facilitiesFor proposed energy conversion facilities for the ensuing 10 calendar years the utility shall provide information as it becomes available as follows:
(1) General location and reasons for the selection;(2) Probable type and nameplate capacity;(3) Projected annual production in megawatt hours;(4) Proposed water source and point of withdrawal, estimated maximum and rate of withdrawal, estimated maximum and annual use and consumption in acre feet;(5) Proposed fuel type and source, estimated maximum and annual consumption of fuel, and, if known, proposed means for transporting fuel to the facility;(6) Proposed plans for waste disposal and monitoring of emissions and wastes, as known;(7) Description of anticipated associated facilities;(8) Projected operating life from fuel source in this state, if any;(9) Projected date of removal from service; and(10) Total estimated capital.S.D. Admin. R. 20:10:21:05
4 SDR 7, effective 11/13/1977; 12 SDR 151, 12 SDR 155, effective 7/1/1986.General Authority: SDCL 49-41B-35.
Law Implemented: SDCL 49-41B-3(1), 49-41B-3(4).