S.D. Admin. R. 20:10:21:05

Current through Register Vol. 51, page 67, December 16, 2024
Section 20:10:21:05 - Proposed energy conversion facilities

For proposed energy conversion facilities for the ensuing 10 calendar years the utility shall provide information as it becomes available as follows:

(1) General location and reasons for the selection;
(2) Probable type and nameplate capacity;
(3) Projected annual production in megawatt hours;
(4) Proposed water source and point of withdrawal, estimated maximum and rate of withdrawal, estimated maximum and annual use and consumption in acre feet;
(5) Proposed fuel type and source, estimated maximum and annual consumption of fuel, and, if known, proposed means for transporting fuel to the facility;
(6) Proposed plans for waste disposal and monitoring of emissions and wastes, as known;
(7) Description of anticipated associated facilities;
(8) Projected operating life from fuel source in this state, if any;
(9) Projected date of removal from service; and
(10) Total estimated capital.

S.D. Admin. R. 20:10:21:05

4 SDR 7, effective 11/13/1977; 12 SDR 151, 12 SDR 155, effective 7/1/1986.

General Authority: SDCL 49-41B-35.

Law Implemented: SDCL 49-41B-3(1), 49-41B-3(4).