Current through Register Vol. 54, No. 45, November 9, 2024
Section 105.103 - Weather and ground conditions(a) No earth or other embankment material may be covered, placed, compacted, or graded when in a frozen condition.(b) Masonry and concrete may not be placed in freezing weather except under conditions approved by the Department.The provisions of this §105.103 adopted September 10, 1971, effective 9/11/1971, 1 Pa.B. 1804; amended August 11, 1978, effective 8/28/1978, 8 Pa.B. 2229; amended September 26, 1980, effective 9/27/1980, 10 Pa.B. 3843; amended January 7, 2011, effective 1/8/2011, 41 Pa.B. 219.The provisions of this §105.103 amended under section 5 of the Dam Safety and Encroachments Act (32 P. S. § 693.5).