Current through Supplement No. 394, October, 2024
Section 69-09-12-02 - Resource plan procedure1. An electric public utility shall file a resource plan on a three-year cycle. The electric public utility may file a supplement to the plan with necessary updates and shall file a supplement upon commission request.2. The commission may investigate a resource plan. Foregoing an investigation or inaction upon completion of an investigation does not bind the commission in the commission's review of a resource plan in conjunction with a rate case or bind the commission for the purpose of setting rates.3. The commission shall issue a notice of opportunity to comment on the resource plan when opening an investigation under subsection 2. The comment period must remain open for a period of sixty days, unless ordered otherwise by the commission.4. During an investigation, an electric public utility may request a commission determination on any issue related to the resource plan. Approval, rejection, or modification of a resource plan, or a commission determination may be presented as prima facie evidence in other proceedings.5. The commission shall designate by order the commencement of the cycle wherein a resource plan must be filed. The commission may allow for a variance from a filing requirement or procedure upon request.N.D. Admin Code 69-09-12-02
Adopted by Administrative Rules Supplement 2022-387, January 2023, effective 1/1/2023.General Authority: NDCC 49-02-04
Law Implemented: NDCC 49-05-04.4, 49-05-17