N.D. Admin. Code 33.1-14-09-11

Current through Supplement No. 394, October, 2024
Section 33.1-14-09-11 - Feedwater connections
1. Feedwater connections must be independent of any water gauge connections and be made to the condensate return pipe or reservoir of the condensate return tank.
2. Alternatively, makeup water or water treatment may be introduced through an independent connection. The water flow from the independent connection may not discharge directly against parts of the boiler exposed to direct radiant heat from the fire. Makeup water or water treatment may not be introduced through openings or connections provided for inspection or cleaning, safety valve, safety relief valve, blowoff, water column, water gauge glass, pressure gauge, or temperature gauge.
3. When there is more than one boiler connected to a system, each boiler must have an independent feedwater line.
4. There must be a stop valve and a check valve in the feedwater line at the boiler. For hot water heating boilers, the check valve must be a backflow preventer approved by the state plumbing board.
5. Hot water heating boilers, not equipped with an approved low-water fuel cutoff, must be equipped with an automatic feeding device or pressure-reducing valve method of feeding, in addition to a manual bypass capable of feeding the boiler at a pressure of six percent above safety relief valve setting.

N.D. Admin Code 33.1-14-09-11

Adopted by Administrative Rules Supplement 2020-377, July 2020, effective 7/1/2020.

General Authority: NDCC 23.1-16