Current through Register Vol. 56, No. 24, December 18, 2024
Section 7:14-2.9 - Mobilization: unit price contracts for sewer construction(a) Mobilization shall consist of the cost of initiating the contract. Payment for mobilization will be made at the lump sum price bid for this item in the proposal, which price shall include the cost of initiating the contract. The provisions for payment for the item mobilization supersede any provisions elsewhere in the specifications for including the costs of these initial services and facilities in the prices bid for the various items scheduled in the proposal. The lump sum price bid for mobilization shall be payable to the contractor whenever he shall have completed 10 percent of the work of the contract. For the purposes of this item, 10 percent of the work shall be considered completed when the total of payments earned, exclusive of the amount bid for this item, shown on the monthly certificates of the approximate quantities of work done, shall exceed 10 percent of the total price bid for the contract.(b) The lump sum price bid for mobilization is limited to the following maximum amounts: Original Contract Amount (including Mobilization) |
From More Than | To and Including | Maximum Amount for Item of |
Mobilization |
$ 0 | $ 100,000 | $ 3,000 |
100,000 | 500,000 | 15,000 |
500,000 | 1,000,000 | 30,000 |
1,000,000 | 2,000,000 | 60,000 |
2,000,000 | 3,000,000 | 90,000 |
3,000,000 | 4,000,000 | 120,000 |
4,000,000 | 5,000,000 | 125,000 |
5,000,000 | 6,000,000 | 150,000 |
6,000,000 | 7,000,000 | 175,000 |
7,000,000 | 10,000,000 | 200,000 |
10,000,000 | -- | 2.5% of Amount Bid |
N.J. Admin. Code § 7:14-2.9