Current through Register No. 45, November 7, 2024
Section Env-A 4711.05 - Action on Monitoring and Verification Reports(a) Within 45 days following receipt of a monitoring and verification report filed pursuant to this part, the regional organization shall review the report to determine whether it contains all required information.(b) If the report is complete, the regional organization shall notify the project sponsor and proceed to a substantive review of the report as specified in (d) and (e), below.(c) If the report is incomplete, the regional organization shall notify the project sponsor in writing of the information that is missing and specify a reasonable deadline for the project sponsor to provide the information. If the project sponsor does not provide the information by the specified deadline, the report shall be rejected and no allowances shall be awarded.(d) After determining that a report is complete, the department shall review the report to determine whether it meets the requirements specified in Env-A 4703 and Env-A 4705 through Env-A 4709, as applicable. If the department determines that the information submitted is inadequate to allow the department to independently conclude that the requirements are met, the department shall direct the regional organization to request such additional information from the project sponsor as is necessary to enable the department to reach a conclusion. If the information is not provided, the report shall be rejected and no allowances shall be awarded.(e) Within 45 days of receiving a complete report, the department shall issue a determination as to whether the report meets the requirements specified in Env-A 4703 and Env-A 4705 through Env-A 4709, as applicable. If the requirements are not met, the determination shall identify the requirement(s) that are not met.N.H. Admin. Code § Env-A 4711.05
#9481, eff 5-23-09; ss by #10469, eff 1-1-14