N.H. Admin. Code § Agr 204.04

Current through Register No. 50, December 12, 2024
Section Agr 204.04 - Computation of Time

Any time period specified in this chapter shall begin with the day following the act, event or default, and shall include the last day of the period, unless it is Saturday, Sunday or a legal state holiday, in which event the period shall run until the end of the next day which is not a Saturday, Sunday or legal state holiday. When the period prescribed or allowed is less than 7 days, intermediate Saturdays, Sundays and state legal holidays shall be excluded from the computation.

N.H. Admin. Code § Agr 204.04

#6299, eff 7-25-96, EXPIRED: 7-25-04

New. #8309-A, eff 3-24-05