Section 704.5683 - Action plan: Deviation from plan by utility
1. Notwithstanding the approval by the Commission of the action plan of a utility, the utility may deviate from the approved action plan to the extent necessary to respond to any significant change in circumstances that was not contemplated by the action plan. A significant change in circumstances includes, without limitation:
(a) A substantial change in the market price of water;
(b) An extended forced outage of a major facility of the utility;
(c) A substantial change in customer demand; or
(d) Any other circumstance that the utility demonstrates to the Commission requires a deviation.
2. If a utility deviates from its approved action plan:
(a) The Commission will determine the prudence of the deviation from the action plan in an appropriate proceeding.
(b) If the deviation from the action plan is of a continuing nature, the utility shall request authority from the Commission to deviate prospectively from the action plan by filing an amendment to the action plan.

Nev. Admin. Code § 704.5683

Added to NAC by Pub. Utilities Comm'n by R043-08, eff. 9-18-2008

NRS 703.025, 704.210, 704.661