Section 704.5682 - Action plan: Action by Commission
1. The Commission will:
(a) Issue an order approving the action plan of a utility as filed;
(b) Issue an order modifying the action plan of a utility; or
(c) Specify those parts of the action plan that the Commission considers inadequate.
2. An action plan shall be deemed to be approved by the Commission only as to that portion of the action plan accepted as filed or modified with the consent of the utility pursuant to subsection 5 of NRS 704.661, as amended by section 2 of Senate Bill No. 87, chapter 230, Statutes of Nevada 2015, at page 1094.
3. If the Commission approves the action plan of the utility, the Commission will include in the approval of the action plan its determination that the elements contained in the action plan are prudent. The Commission will make a determination that the elements of the action plan are prudent if:
(a) The action plan maximizes the utility's water supply and wastewater treatment capacities for the benefit of the utility's customers; and
(b) The utility demonstrates that the action plan balances the objectives of minimizing cost, mitigating risk and maximizing reliability of service for the term of the action plan.
4. If the Commission subsequently determines that any information relied upon when issuing its order approving or modifying the action plan was based upon information that was known or should have been known by the utility to be false when the information was presented, the Commission may revoke, rescind or otherwise modify its approval of the action plan.

Nev. Admin. Code § 704.5682

Added to NAC by Pub. Utilities Comm'n by R043-08, eff. 9-18-2008; A by R110-15, eff. 6/28/2016

NRS 703.025, 704.210 and 704.661, as amended by section 2 of Senate Bill No. 87, chapter 230, Statutes of Nevada 2015, at page 1094.