Nev. Admin. Code § 445B.248

Current through October 11, 2024
Section 445B.248 - Reconstruction: Determination of whether replacement constitutes reconstruction
1. The Director will determine, within 30 days of the receipt of the notice required by subsection 2 of NAC 445B.247 and any additional information he or she may reasonably require, whether the proposed replacement constitutes reconstruction.
2. The Director's determination under subsection 1 must be based on:
(a) The fixed capital cost of the replacements in comparison to the fixed capital cost that would be required to construct an entirely new comparable facility;
(b) The estimated life of the facility after the replacements compared to the life of an entirely new comparable facility;
(c) The extent to which the components being replaced cause or contribute to the emissions from the facility; and
(d) Any economic or technical limitations on compliance with applicable standards of performance which are inherent in the proposed replacements.

Nev. Admin. Code § 445B.248

Environmental Comm'n, Air Quality Reg. §§ 2.15.5-2.15.6.4, eff. 12-4-76-NAC R 12-13-93, eff. 11-15-94; A 10-30-95-Substituted in revision for NAC 445.680

NRS 445B.210, 445B.300