Current through October 11, 2024
Section 445A.269 - Notice of requirement to obtain individual permit; grant of additional time1. If the holder of a general permit is required to obtain an individual permit pursuant to NRS 445A.480, the Director must inform the holder of the requirement by written notice. The written notice must include: (a) A brief statement of the reasons for the decision to require an individual permit;(b) An application form for an individual permit;(c) The fee schedule of an application for an individual permit;(d) The time by which the application must be received by the Department; and(e) A statement that coverage by the general permit expires on the effective date of the individual permit.2. The Director may grant additional time for good cause upon request by the holder of the general permit.Nev. Admin. Code § 445A.269
Added to NAC by Environmental Comm'n, eff. 3-18-92-Substituted in revision for NAC 445.1753NRS 445A.425, 445A.465, 445A.480