137 Neb. Admin. Code, ch. 8, § 006

Current through September 17, 2024
Section 137-8-006

Any grant contract which includes a construction project may require, but not be limited to, the following special conditions:

006.01 Final plans and specifications shall be approved by the Executive Director. The Executive Director may require that plans and specifications be stamped by a Professional Engineer registered to practice in the State of Nebraska.
006.02 A construction schedule including commencement of construction; accountability for inspection during construction; construction completion; and initiation of operation (if applicable).
006.03 The Executive Director may provide a contingency within the grant for change orders.
006.03(A) All change orders must be approved by the Executive Director in a manner set out within the grant contract.
006.04 Upon completion of the project, a certification of completion shall be filed with the Board, which certifies that construction was substantially consistent with the approved plans and specifications. The certification shall be signed by the grantee. The Executive Director may also require a certification signed by a Professional Engineer registered to practice in the State of Nebraska.

137 Neb. Admin. Code, ch. 8, § 006

Amended effective 5/8/2018
Amended effective 8/12/2023