Section 26.03.12.03 - General Requirements
A. Permit. A person shall have a permit issued by the Department under Environment Article, § 9-204, Annotated Code of Maryland, before the person installs, materially alters, or materially extends a major water supply system or major sewerage system within the State.
B. Construction in Accordance with Permit. Within the State, a person may not:
(1) Install, materially alter, or materially extend a major water supply system or major sewerage system except in accordance with a permit, and including any conditions or requirements set forth in the permit, issued to the person by the Department under Environment Article, § 9-204, Annotated Code of Maryland; or
(2) Embody any material change in construction until the Department has issued a revised permit based on the submission to the Department of any material change in the plans and specifications, together with the reason for the change.
C. Capacity Development Assessment Program. Before a permit may be issued under Environment Article, § 9-204, Annotated Code of Maryland, for new major water supply systems, a permit applicant shall demonstrate to the satisfaction of the Department that it has the technical, financial, and managerial capacity to operate the system as required by COMAR 26.04.01.36.

Md. Code Regs. 26.03.12.03

Regulation .03C adopted effective October 4, 1999 (26:20 Md. R. 1548)