La. Admin. Code tit. 56 § V-905

Current through Register Vol. 50, No. 11, November 20, 2024
Section V-905 - Applicability of Requirement for Permits and Plans
A. Permits are required for all nonexempt wells drilled in the parishes of Ascension, East Baton Rouge, East Feliciana, Pointe Coupee, West Baton Rouge, West Feliciana, and any other parishes that may be admitted to the Capital Area Groundwater Conservation District. The permit application for the proposed well shall be accompanied by a set of plans to include at a minimum:
1. location of proposed well to the nearest second of latitude and longitude;
2. location of existing water wells within 1000 feet;
3. proposed depth;
4. casing and screen sizes and approximate depths;
5. proposed well yield and average daily pumpage;
6. piping layout geometry for the site;
7. a horizontal section of pipe for installation of the metering device and remote monitoring system shall be located downstream from the backflow preventer. The length and location of pipe shall be requested in the application and presented to the commission for approval; and
8. site layout which includes a location of a six-foot-by-six-foot slab for installation of monitoring equipment.

La. Admin. Code tit. 56, § V-905

Promulgated by the Office of the Governor, Capital Area Ground Water Conservation Commission, LR 2:76 (March 1976), repromulgated LR 33:2648 (December 2007), Amended LR 491916 (11/1/2023).
AUTHORITY NOTE: Promulgated in accordance with R.S. 38:3076(14) and 38:3079, amended in accordance with R.S. 38:3076.A(2) 38:3076.A(5), and 38:3076.E.