La. Admin. Code tit. 43 § XIII-7913

Current through Register Vol. 50, No. 11, November 20, 2024
Section XIII-7913 - Auxiliary Power Sources [49 CFR 193.2613]
A. Each auxiliary power source must be tested monthly to check its operational capability and tested annually for capacity. The capacity test must take into account the power needed to start up and simultaneously operate equipment that would have to be served by that power source in an emergency. [ 49 CFR 193.2613 ]

La. Admin. Code tit. 43, § XIII-7913

Promulgated by the Department of Natural Resources, Office of Conservation, LR 441056 (6/1/2018).
AUTHORITY NOTE: Promulgated in accordance with R.S. 30:551.C.