La. Admin. Code tit. 43 § XIII-1709

Current through Register Vol. 50, No. 11, November 20, 2024
Section XIII-1709 - Repair of Steel Pipe [49 CFR 192.309]
A. Each imperfection or damage that impairs the serviceability of a length of steel pipe must be repaired or removed. If a repair is made by grinding, the remaining wall thickness must at least be equal to either: [ 49 CFR 192.309(a)]
1. the minimum thickness required by the tolerances in the specification to which the pipe was manufactured; or [ 49 CFR 192.309(a)(1)]
2. the nominal wall thickness required for the design pressure of the pipeline. [ 49 CFR 192.309(a)(2)]
B. Each of the following dents must be removed from steel pipe to be operated at a pressure that produces a hoop stress of 20 percent, or more, of SMYS unless the dent is repaired by a method that reliable engineering tests and analyses show can permanently restore the serviceability of the pipe: [ 49 CFR 192.309(b)]
1. a dent that contains a stress concentrator such as a scratch, gouge, groove, or arc burn; [ 49 CFR 192.309(b)(1)]
2. a dent that affects the longitudinal weld or a circumferential weld; [ 49 CFR 192.309(b)(2)]
3. in pipe to be operated at a pressure that produces a hoop stress of 40 percent or more of SMYS, a dent that has a depth of: [ 49 CFR 192.309(b)(3)]
a. more than 1/4 inch (6.4 millimeters) in pipe 12 3/4 inches (324 millimeters) or less in outer diameter; or [ 49 CFR 192.309(b)(3)(i)]
b. more than 2 percent of the nominal pipe diameter in pipe over 12 3/4 inches (324 millimeters) in outer diameter. [ 49 CFR 192.309(b)(3)(ii) ]
C. For the purpose of this Section a "dent" is a depression that produces a gross disturbance in the curvature of the pipe wall without reducing the pipe-wall thickness. The depth of a dent is measured as the gap between the lowest point of the dent and a prolongation of the original contour of the pipe.
D. Each arc burn on steel pipe to be operated at a pressure that produces a hoop stress of 40 percent, or more, of SMYS must be repaired or removed. If a repair is made by grinding, the arc burn must be completely removed and the remaining wall thickness must be at least equal to either: [ 49 CFR 192.309(c)]
1. the minimum wall thickness required by the tolerances in the specification to which the pipe was manufactured; or [ 49 CFR 192.309(c)(1)]
2. the nominal wall thickness required for the design pressure of the pipeline. [ 49 CFR 192.309(c)(2)]
E. A gouge, groove, arc burn, or dent may not be repaired by insert patching or by pounding out. [ 49 CFR 192.309(d)]
F. Each gouge, groove, arc burn, or dent that is removed from a length of pipe must be removed by cutting out the damaged portion as a cylinder. [ 49 CFR 192.309(e)]

La. Admin. Code tit. 43, § XIII-1709

Promulgated by the Department of Natural Resources, Office of Conservation, LR 9:232 (April 1983), amended LR 10:524 (July 1984), LR 18:857 (August 1992), LR 27:1542 (September 2001), LR 30:1245 (June 2004).
AUTHORITY NOTE: Promulgated in accordance with R.S. 30:501 et seq.