Current through Register Vol. 50, No. 11, November 20, 2024
Section XIII-1707 - Inspection of Materials [49 CFR 192.307]A. Each length of pipe and each other component must be visually inspected at the site of installation to ensure that it has not sustained any visually determinable damage that could impair its serviceability. [ 49 CFR 192.307]La. Admin. Code tit. 43, § XIII-1707
Promulgated by the Department of Natural Resources, Office of Conservation, LR 9:232 (April 1983), amended LR 10:524 (July 1984), LR 30:1245 (June 2004).AUTHORITY NOTE: Promulgated in accordance with R.S. 30:501 et seq.