329 Ind. Admin. Code 11-11-2

Current through December 4, 2024
Section 329 IAC 11-11-2 - Issuance procedures; renewal permits

Authority: IC 13-14-8-7; IC 13-15-2-1; IC 13-19-3-1; IC 13-19-4-10

Affected: IC 13-20-8; IC 13-30-2; IC 36-9-30

Sec. 2.

(a) After the commissioner concludes that the renewal application is complete, the following is required:
(1) The commissioner shall comply with the procedural requirements of IC 13 relevant to an application for a renewal permit for a solid waste incinerator regulated under IC 13-20-8.
(2) The commissioner shall review the application to determine whether the facility or operation is in compliance with the plans and specifications as approved in its existing permit. The commissioner may request clarification or supplementation of information submitted in support of the renewal application. The commissioner shall evaluate the facility's compliance record under:
(A) the operational requirements of 329 IAC 11-7, 329 IAC 11-13, 329 IAC 11-14, 329 IAC 11-15, 329 IAC 11-19, and 329 IAC 11-20 as appropriate; and
(B) any prior or existing permit conditions.
(b) After the provisions of subsection (a) have been accomplished, if the commissioner determines that the facility will be in compliance with the requirements of this article and the permit conditions, including any additions to or revisions of the conditions in the existing permit, the commissioner shall grant renewal of the permit.
(c) All renewal permits must be issued in the name of the owner of the facility.

329 IAC 11-11-2

Solid Waste Management Board; 329 IAC 11-11-2; filed Mar 14, 1996, 5:00 p.m.: 19 IR 1940; readopted filed Nov 16, 2001, 4:43 p.m.: 25 IR 1130, eff Jan 1, 2002; readopted filed May 14, 2007, 1:53 p.m.: 20070523-IR-329070138BFA
Readopted filed Jun 6, 2016, 11:52 a.m.: 20160706-IR-329160144BFA