Sec. 87.

(a) An exploratory or monitoring well may only be transferred by the person who conducts underground mining activities for further use as a permanent water well with the prior approval of the director. That person and the surface owner of the lands where the well is located shall jointly submit a written request to the director for that approval.
(b) Upon an approved transfer of a well, the transferee shall:
(1) assume primary liability for damages to persons or property from the well;
(2) plug the well when necessary, but in no case later than abandonment of the well; and
(3) assume primary responsibility for compliance with sections 72 through 74 of this rule with respect to the well.
(c) Upon an approved transfer of a well, the transferor shall be secondarily liable for compliance with sections 72 through 74 of this rule until release of the bond or other equivalent guarantee required by 312 IAC 25-5 for the area in which the well is located.