Section 312 IAC 25-6-83 - Underground mining; hydrologic balance; acid-forming and toxic-forming materialsAuthority: IC 14-34-2-1
Affected: IC 14-34
Sec. 83.
Drainage from acid-forming and toxic-forming underground development waste and spoil, if any, into ground and surface water shall be avoided by doing the following:
(1) Identifying, burying, and treating, where necessary, waste and spoil that, in the judgment of the director, may be detrimental to vegetation, or may adversely affect water quality, if not treated or buried.(2) Preventing water from coming into contact with acid-forming and toxic-forming materials in accordance with section 112 of this rule.(3) Burying or treating all acid-forming or toxic-forming spoil within a reasonable period of time. If the director determines that such spoil is detrimental to the offsite hydrologic balance, the operator shall bury or treat the acid-forming or toxic-forming spoil within thirty (30) days.Natural Resources Commission; 312 IAC 25-6-83; filed Jun 21, 2001, 2:53 p.m.: 24 IR 3553, eff Dec 1, 2001; readopted filed May 29, 2007, 9:51 a.m.: 20070613-IR-312070146RFA; readopted filed Sep 19, 2013, 10:12 a.m.: 20131016-IR-312130125RFAReadopted filed 3/26/2019, 3:40 p.m.: 20190424-IR-312190011RFA