Sec. 27.
Before abandoning a permit area or seeking bond release, the person who conducts the surface mining activities shall ensure that all temporary structures are removed and reclaimed, and that all permanent sedimentation ponds, diversions, impoundments, and treatment facilities meet the requirements of this article for permanent structures, and have been maintained properly and meet the requirements of the approved reclamation plan for permanent structures and impoundments. The person who conducts the underground mining activities shall renovate such structures if necessary to meet the requirements of this article and to conform to the approved reclamation plan.
312 IAC 25-6-27