170 Ind. Admin. Code 8.5-4-26

Current through December 4, 2024
Section 170 IAC 8.5-4-26 - Free extension

Authority: IC 8-1-2-47; IC 8-1-2-69; IC 8-1-2-89

Affected: IC 8-1-1-3; IC 8-1-2-89

Sec. 26.

A utility, upon written request for service by an applicant, shall extend a main and connect the applicant free of charge to provide the service requested if:

(1) the cost of the main extension does not exceed the immediate revenue allowance for the applicant; and
(2) the applicant agrees to take service within nine (9) months following the completion date of the main extension.

170 IAC 8.5-4-26

Indiana Utility Regulatory Commission; 170 IAC 8.5-4-26; filed Dec 5, 1990, 3:35 p.m.: 14 IR 569; readopted filed Jul 11, 2001, 4:30 p.m.: 24 IR 4233; readopted filed Apr 24, 2007, 8:21 a.m.: 20070509-IR-170070147RFA; readopted filed Aug 2, 2013, 2:16 p.m.: 20130828-IR-170130227RFA
Readopted filed 4/11/2019, 9:04 a.m.: 20190508-IR-170190136RFA