Section 170 IAC 4-6-12 - Ratemaking treatment; initial application testimony and exhibits

Authority: IC 8-1-2-6.6

Affected: IC 8-1-2; IC 8-1.5-3-8

Sec. 12.

A utility shall submit the following to the commission as part of its prefiled written testimony and exhibits in support of its request under section 11 of this rule:

(1) The value of the qualified pollution control property under construction for which the utility is seeking ratemaking treatment.
(2) The computation of the AFUDC amounts included in the value of the qualified pollution control property under construction for which the utility is seeking ratemaking treatment, including the derivation of the associated AFUDC rate.
(3) A list of the qualified pollution control property projects under construction, including the following for each project:
(A) The anticipated inservice dates.
(B) The stages of completion.
(C) The qualified pollution control property values for which the utility is seeking ratemaking treatment.
(4) The derivation of the utility's weighted cost of capital, including the amounts, proportions, and cost rates for each of the utility's capital structure components used in the derivation of the utility's weighted cost of capital incorporated in the utility's request for ratemaking treatment of the value of its qualified pollution control property under construction.
(5) The derivation of the utility's revenue requirement, including tax calculations, associated with the ratemaking treatment of the value of the qualified pollution control property under construction.
(6) The method and allocation of the utility's revenue requirement associated with the proposed ratemaking treatment of the value of qualified pollution control property under construction among the utility's customer classes.
(7) Proposed amendments to the utility's rate schedules on file with the commission that would reflect the proposed ratemaking treatment of the value of qualified pollution control property under construction.
(8) Any other information, calculations, written testimony, or exhibits requested by the commission.

170 IAC 4-6-12

Indiana Utility Regulatory Commission; 170 IAC 4-6-12; filed Oct 5, 1993, 5:00 p.m.: 17 IR 178; readopted filed Jul 11, 2001, 4:30 p.m.: 24 IR 4233; readopted filed Apr 24, 2007, 8:21 a.m.: 20070509-IR-170070147RFA; readopted filed Aug 2, 2013, 2:16 p.m.: 20130828-IR-170130227RFA
Readopted filed 4/11/2019, 9:04 a.m.: 20190508-IR-170190136RFA